§ 16.28.030. Submittal and approval by city engineer.
Latest version.
The amending map or certificate of correction, complete as to final form, shall be
submitted to the city engineer for review and approval. The city engineer shall examine
the amending map or certificate of correction and if the only changes made are those
permitted by Section 16.28.010 of this chapter, the city engineer shall certify that fact on the amending map or
certificate of correction. The city engineer shall examine each certificate of correction
for compliance with the provisions of this chapter and the Subdivision Map Act, endorse
a statement on it of his or her examination and certification, and present it to the
county recorder for recordation within twenty working days after its submittal. If
the submitted certificate fails to comply with the provisions of this chapter or the
Subdivision Map Act, the city engineer shall return it within the same twenty working
days to the person who presented it, together with a written statement of the changes
necessary to make it conform to the requirements of this chapter or the Subdivision
Map Act. The licensed land surveyor or registered civil engineer submitting the certificate
of correction may then make the necessary changes and resubmit the certificate of
correction to the city engineer for approval. If the resubmitted certificate is approved,
the city engineer shall present it to the county recorder for recordation within ten
working days.